Commissioning

Only use original parts and accessories.

Before you begin

To operate the device in a cybersecure environment, take the following measures before commissioning:

  • Change default user and add a strong password. Secure the password in a safe location.

  • Check if the device is running the latest firmware version. If not, update the firmware to the latest version that fits your needs.

  • Set the brute force protection configuration to values that fit your needs.

  • Replace the default self-signed certificate with a root certificate that is trusted by your organization. Secure the private key in a safe location.

Post-commissioning measures

In order to maintain a secure environment, take the following measures after commissioning:

  • Create a backup of the device configuration and store it in a secure location.

Adjustability of zero point

Check the indicated zero point on the digital display during commissioning. Should a zero point offset be displayed as a result of installation, this can be reset in programming mode with the 0SET parameter. Only carry out the setting for gauge and vacuum pressure measuring ranges in a depressurised state.

Note

For absolute pressure measuring ranges, the setting must be carried out at 0 bar absolute (vacuum). Since appropriate references are required for this, we recommend that this is only carried out by the manufacturer.